2) Table below lists the sequence of machine types required for nine part types and also shows the annual volume of production for each.
TABLE 6.10 — Part Routing and Volume Information for Exercise 7
Part Type Number
Sequence of Machine Types Visited
Production Volume
1
3,5,2
3000
2
3,5
1000
3
4, 6, 1
8550
4
1,4
2750
5
6,4
9000
6
1,6
500
7
2,5,3
300
8
5,3
3600
9
6, 1, 4
4110
a) Set up a part machine matrix for this data.
b) Assuming the transfer batch size for part types 1-4 is 30, part types 5-8 is 15, and part type 9 is 10, determine the frequency of trips matrix using the matrix that was set up in (a).