➤ How do I construct a project network from activity lists and predecessors?
Start by listing each activity with its immediate predecessors and duration. Draw nodes or arrows to reflect those precedence relationships. Insert dummy activities when you need to show logical links without time. Perform forward and backward passes to compute early and late times, then calculate floats to reveal the critical path.