The Contractor wishes to replace a key person named in the Contract Data. Which ONE of the following best describes the actions now required by the Contractor and Project Manager? Select ONE option
The Contractor should submit the name, relevant qualifications and experience of the proposed replacement to the Project Manager for approval. The Project Manager should respond within two weeks and accept or not accept the replacement person. A reason for not accepting the person is that their qualifications and experience are not as good as those of the person who is to be replaced.
The Contractor should submit the name, relevant qualifications and experience of the proposed replacement to the Project Manager for acceptance. The Project Manager should respond within the period for reply and accept the proposed replacement providing the person’s qualifications and experience are as good as the person being replaced.
If the Project Manager is prepared to consider the proposed replacement, the Project Manager should instruct the Contractor to submit the name, relevant qualifications and experience of the proposed replacement to the Project Manager for acceptance. The Project Manager should accept the proposed replacement providing the person’s qualifications and experience are as good as the person being replaced.
The Project Manager should first consult with the Client on the proposed replacement. If the Client is prepared to consider the proposed replacement, the Project Manager should instruct the Contractor to submit the name, relevant qualifications and experience of the proposed replacement to the Project Manager for acceptance. The Project Manager should accept the proposed replacement providing the person’s qualifications and experience are as good as the person being replaced.