Activity Predecessor duration months= (o+(4*m)+p)/6 A — 7 B — 6 C — 32 D B 22 E C 4 F D 9 G A,B 12…

Written by

in

Activity Predecessor duration months= (o+(4*m)+p)/6
A — 7
B — 6
C — 32
D B 22
E C 4
F D 9
G A,B 12
H E 10
I G 7
J F,G 10
calculate slack time, LS and LF show working