➤ How do companies calculate dependent demand for components?
They “explode” the bill of materials by multiplying the master production schedule quantities by component usage per unit. Then they subtract on-hand inventory, add scheduled receipts, and account for scrap and safety stock. The result gives net requirements and planned orders that feed MRP replenishment and lot-sizing decisions.