You own a Bakery, here is the process: Mix 500/hr, Bake 600/hr, Slice 400/hr, Package 800/hr. Which…

Written by

in

➤ How do I calculate overall throughput and utilization?
Overall throughput equals the minimum capacity across stages, so this line produces 400 units per hour. Calculate utilization by dividing throughput by each step’s capacity: mixing 400/500 = 80%, baking 400/600 = 67%, slicing 400/400 = 100%, packaging 400/800 = 50%.