1.What information is required to create a CPM (choose all that apply) Question 1 options: List of Tasks (Activities) Durtion of the Tasks (Activities) What coloc the bars on the bar chart will be. Relationship between the Tasks (Activities)
List of Tasks (Activities)
Durtion of the Tasks (Activities)
What coloc the bars on the bar chart will be.
Relationship between the Tasks (Activities)
2. One way to break up the work into tasks (Activities) is to consider unique crew or trade. Question 2 options: True False
True
False
3.WBS stands for ________________. Question 3 options: Week Before Start Wednesday is Bowling for Sundays Work Benefit Subscription Work Breakdown Structure
Week Before Start
Wednesday is Bowling for Sundays
Work Benefit Subscription
Work Breakdown Structure
4. Every network has at least one critical path. Question 4 options: True False
True
False
5. The forward pass defines Early Start and Early Finish dates. Question 5 options: True False
True
False
6. Task B is the only predecessor to Task C. Task B has an early finish of day 10. What is the early start of its’ successor task C? Question 6 options cannot be determined from given information. 11 9 10
cannot be determined from given information.
11
9
10
7. Task E has a duration of 3 days. The late finish of task E is day 7. What is the late start of task E? Question 7 options: 4 cannot be determined from given information 3 10
4
cannot be determined from given information
3
10
8.Task F has a duration of 3 days. The early start of task F is day 13. What is the early finish? Question 8 options: 16 6 cannot be determined from given information. 10
16
6
cannot be determined from given information.
10
9. What is usually the start of contract time? Question 9 options: Notice to Pay Substantial Start Substantial Completion Notice to Proceed
Notice to Pay
Substantial Start
Substantial Completion
Notice to Proceed
10.What usually denotes the end of contract time. Question 10 options: Notice to Pay Substantial Succession Notice to Proceed Substantial Completion
Notice to Pay
Substantial Succession
Notice to Proceed
Substantial Completion
11. Total Float is the difference between __________________. Question 11 options: Late Start – Late Finish Early Start + Duration Late Finish and Late Start of the successor Early Start and Late Start of an activity
Late Start – Late Finish
Early Start + Duration
Late Finish and Late Start of the successor
Early Start and Late Start of an activity
12. Tasks A, B, D, u0026 F all have zero float on a project. There are no other tasks with less float. This series of tasks is most likely the critical path. Question 12 options: True False
True
False
13. Task A is a predecessor to Task B. You have a start to start relationship between the two tasks. What is true about their relationship? Question 13 options: Task B must finsih before A can start. Task A must start before B can finish. Task A must start before B can start. Task B must start before A can start
Task B must finsih before A can start.
Task A must start before B can finish.
Task A must start before B can start.
Task B must start before A can start
14. A mileston task consumes no time. Question 14 options: True False
True
False
15.One reason Bar Charts are not useful because they are difficult to understand. Question 15 options: True False
True
False
16.CPM requires that tasks have clearly defined relationships between them. Question 16 options: True False
True
False