Inventory on Hand: None Routing File: Work Center Master File: * Aaverage efficiency is based on processing time only. A . Create a Capacity Bill ( using lot sizes ) for Z in the box provided. 5 pts B . How much nominal capacity ( in hours ) is required of Work Center 4 0 to complete an order for 6 5 0 Z ‘ s . ( Consider both set – up and run time ) B . The Master Production Schedule ( MPS ) calls for 4 0 0 units in Week 1 and 5 0 0 in Week 2 of product Z . Fill in the Workcenter loads ( minutes ) for the two weeks in the table below. Can you fulfill the MPS ? Explain. 5 pts . D . Given the current resources and inventories available, how many Z ‘ s could be produced if all resources are utilized for their production? ( 5 pts . )