The manager of a local youth sports organization is planning its basketball season. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows. Time (weeks) Activity/Description Predecessor(s Optim. Most Likely Pessim. A Meet with board B – Interview/hire coaches C – Reserve facilities D – Create schedule E Meet with coaches F Register players G-Order uniforms H Collect fees I – Organize first practice 2.0 6.0 5.0 2.5 4.0 4.0 3.0 3.0 2.0 1.0 3.0 2.0 1.5 2.0 1.0 1.0 1.0 0.5 1.5 4.0 3.0 2.0 3.0 2.0 2.0 2.0 1.0 B, C E, F, H
(a) Draw the project network diagram. (b) Compute the mean and variance of the duration of each activity. You may do this by hand or by using technology, such as Excel. (c) Determine the critical path, the expected project completion time, and the variance of the project completion time. (d) What is the probability that the project can be completed within 11.8 weeks? (e) What is the probability that the project takes longer than 14.5 weeks to complete? (f) If the manager wants a 96.5% probability of completing the project on time, how far ahead of the first practice should she start working?
Leave a Reply