Question 116Consider the following information on job times and due dates (in…

Written by

in

➤ Is it possible for SPT and EDD to produce the same sequence, and what does that imply?
Yes. If short jobs also have the earliest due dates, SPT and EDD can yield the same order. In that case both average flow time and average tardiness will be identical for the instance. If sequences differ, evaluate completion times, average flow time, and average tardiness to determine which rule is preferable.

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *